Lawrence Berkeley National Laboratory masthead Search Jobs Phone Book U.S. Department of Energy logo Berkeley Lab masthead A-Z Index

Environmental Restoration Program

Photo Gallery

INTERIM CORRECTIVE MEASURES (ICMs)

SOIL FLUSHING PILOT TESTS: Building 64


Building 64 Soil Flushing Pilot Test
Groundwater collection trench has been excavated to 4 feet to expose and remove underground utilities.

 

 


Building 64 Soil Flushing Pilot Test
Abandoned electric conduits crossing the site of the groundwater collection trench.

 

 


Building 64 Soil Flushing Pilot Test
A 24-inch shaft is being drilled for construction of the groundwater collection trench.

 

 


Building 64 Soil Flushing Pilot Test
Construction of injection trench inside Building 64.

 