§1.03
Plant Construction, Maintenance, and Service

Responsible Manager


Rev. 12/01

  1. Plant Construction and Alterations
  2. Repair and Maintenance Work
    1. General
    2. Special Research Equipment
  3. Miscellaneous Services
  4. Response to Power Reduction Alerts

A.  PLANT CONSTRUCTION AND ALTERATIONS

The Facilities Division is responsible for all construction and alterations to Laboratory buildings, infrastructure, utilities, and building systems except for those systems specifically assigned to other divisions/departments (e.g., telephone and ProxCard). Requests for plant construction and alteration work are made to the Facilities Division's Work Request Center.

B.  REPAIR AND MAINTENANCE WORK

1.  General

The Facilities Division is responsible for maintenance and repair of plant facilities and equipment, including buildings, grounds, utility systems, roadways, walks, fences, and plant mechanical and electrical equipment. Requests for such work are made to the Facilities Division's Work Request Center.

2.  Special Research Equipment

The Facilities Division performs maintenance and repair work on specialized research equipment when requested by a responsible member of the group having charge of the equipment. Requests for such work are made to the Facilities Division's Work Request Center.

C.  MISCELLANEOUS SERVICES

Service functions are assigned to the divisions shown in RPM Table 1.03(C) (Service Functions).

 

Table 1.03(C)
Service Functions

Type of service Division responsible
Vehicle Fleet Operations    Facilities
Bus Service Facilities
Nonstandard Vehicle Operator's Certification Environment, Health, and Safety
Locksmith and Key Issuance and Records Facilities
Electric Light Service Facilities
Building Custodial Service Facilities
Groundskeeping Facilities
Refuse Disposal Facilities
Parking Permit Issuance and Records Environment, Health, and Safety
Transportation Facilities
Mail Services Facilities
Central Stores Facilities

D.  RESPONSE TO POWER REDUCTION ALERTS

The Facilities Division is responsible for implementing the Laboratory's response plan to Stage I, II, and III electrical emergency alerts issued by California's Independent System Operator and communicated to Berkeley Lab by the Western Area Power Administration. The Facilities Division is also responsible for updating the Laboratory's response plan.