Helios facility rendering  

Project Description

The Helios Energy Research Facility Project would be located in the southeastern portion of LBNL.  The proposed project includes a 145,000 gross-square-foot building, an access road, and a parking lot.  The proposed building would house research programs focused primarily on alternative and renewable energy sources.

Additional Information

 

FINAL EIR

Berkeley Lab Final Environmental Impact Report
on the Proposed Construction and Operation of the
Helios Energy Research Facility project
Date Issued Document Title Comment Period
April 2008 PDF iconCover Page  
April 2008 PDF iconTitle Page; Table of Contents; Chapter 1.0: Introduction  
April 2008 PDF iconChapter 2.0: Project Refinements  
April 2008 PDF iconChapter 3.0: Revisions to the Draft EIR  
April 2008 PDF iconChapter 4.0: Comments to the Draft EIR and Responses to Comments  
April 2008 PDF iconChapter 5.0: Mitigation Monitoring and Reporting Program; Chapter 6.0: Preparers; Chapter 7.0: References  
April 2008 PDF iconAppendix A: Westlaw Search for Cultural Landscape Cases; Appendix B: Transportation and Circulation Memorandums  
April 2008 PDF iconAttachments  
April 2008 PDF iconAttachments  
April 2008 PDF iconAttachments  


DRAFT EIR

Berkeley Lab Draft Environmental Impact Report
on the Proposed Construction and Operation of the
Helios Energy Research Facility project
Date Issued Document Title Comment Period
12/17/07 PDF iconHelios Public Hearing Presentation 11/16/2007
to
02/01/2008
12/14/07 PDF iconNotice of Public Review Period Extension 11/16/2007
to
02/01/2008
11/19/2007 PDF icon3.0 Project Description 11/19/2007
to
02/01/2008
11/19/2007 PDF icon4.0 Environmental Setting, Impacts, and Mitigation Measures 4.1 Aesthetics, 4.2 Air Quality, 4.3 Biological Resources, 4.4 Cultural Resources, 4.5 Geology and Soils, 4.6 Hazards 11/19/2007
to
02/01/2008
11/19/2007 PDF icon4.7 Hydrology and Water Quality 11/19/2007
to
02/01/2008
11/19/2007 PDF icon4.8 Land Use and Planning 11/19/2007
to
02/01/2008
11/19/2007 PDF icon4.9 Noise 11/19/2007
to
02/01/2008
11/19/2007 PDF icon4.10 Population and Housing, 4.11 Public Services, 4.12 Transportation and Traffic, 4.13 Utilities and Service Systems 11/19/2007
to
02/01/2008
11/19/2007 PDF icon5.0 Cumulative Impacts, 6.0 Alternatives, 7.0 Other CEQA Considerations, 8.0 Organizations and Persons Consulted, 9.0 Report Preparation, 10.0 Acronyms 11/19/2007
to
02/01/2008
11/19/2007 PDF iconAppendices 11/19/2007
to
02/01/2008
08/08/2007 PDF iconScoping Meeting Transcript and Scoping Comments (2 files) 08/08/2007
to
09/08/2007
     
8 Aug 2007 PDF iconCEQA Presentation  
8 Aug 2007 PDF iconScoping Meeting Presentation on the Helios Facility

PDF iconThe Helios Building: Science for a Sustainable Planet
 
26 Jul 2007 PDF iconScoping Meeting Announcement
 
26 Jul 2007 PDF iconNOTICE OF PREPARATION, ENVIRONMENTAL IMPACT REPORT
 
26 Jul 2007 PDF iconAPPENDIX A: MITIGATION MEASURES, ENVIRONMENTAL IMPACT REPORT